Official Statement
Government of Guyana has failed to pay EUR 45.53 million in construction invoices
Vienna, 7 August 2026 – 14:07
EN
The Government of Guyana, led by the Minister of Health, has failed to pay construction invoices totalling EUR 45.53 million that have been due since October 2025.
Even after ten months and endless negotiations, the Government of Guyana has still not paid the outstanding construction invoices.
This is surprising, given that the engineering firm commissioned by the government had only recently certified EUR 39 million of these as valid.
Due to these failings, work on both hospitals has been scaled back. Legal action is underway.
“They have underlying problems throughout the Ministry of Health.”
— Kenneth Knauer, 53, on site in Guyana
Further information on the current status will follow.
DE
Guyanas Regierung angeführt durch den Gesundheitsminister zahlt seit Oktober 2025 fällige Baurechnungen zu EUR 45,53 Mio. nicht.
Auch nach zehn Monaten und unendlichen Verhandlungen zahlt die Regierung Guyanas die ausstehenden Bau-Rechnungen nicht.
Verwunderlich: Denn die von der Regierung beauftragte Ingenieurgesellschaft hatte gerade kürzlich EUR 39 Mio. davon als berechtigt bescheinigt.
Wegen dieser Verfehlungen wurden die Arbeiten an beiden Hospitals heruntergefahren. Klage ist unterwegs.
“They have underlying problems throughout the Ministry of Health.”
— Kenneth Knauers (53) vor Ort in Guyana
Weitere Informationen folgen zum Sachstand.